Pipeline construction
Commencement date: 2008
Completion date: December 2009
Works performed by ECC‐VECO under the Project:
- ROW preparation;
- pipe joint welding;
- construction and installation of temporary crossings and bridges;
- pipe and cable laying across the Piltun bay (10 km);
- main pipeline welding and laying (79 km);
- electrical and chemical protection system installation;
- construction and installation works on pipeline and cable laying in OPF PA;
- ROW reclamation;
- rigging off temporary crossings and bridges.