First Stage Production
Commencement date: June 2009
Completion date: December 2011
The following was performed as part of the project:
- Installation, construction, fabrication, testing, setup, turnover and commissioning of the following key components:
- Infrastructure and early field works (roads, bridges etc.);
- Well site facilities;
- First stage production facilities (process and non-process).
- The supply, rental and maintenance of all site establishment and temporary construction facilities required for the performance of Work, including, but not limited to the following: site offices, warehouse, change rooms, waste disposal containers, canteen, utilities, showers, toilets, consumables, expendables, furniture, copiers, telephone, installation and fax machines, safety and control systems.
- Camp construction and maintenance. Maintenance and operation of the temporary base.
- Assembly and erection of modular substations and LERs;
- Heating, ventilation, air conditioning system installations;
- Installation, erection, leveling/alignment, grouting, check out, testing and maintenance of all the mechanical equipment and other similar services.